# Underfloor Heating Commissioning Protocol Before Parquet

> Why you must follow the underfloor heating commissioning protocol (first heating) before laying parquet or tiles in your new Croatian house.

- Canonical URL: https://bldr.hr/blog/underfloor-heating-commissioning-protocol-croatia/
- Language: en
- Page type: article
- Primary topic: underfloor heating commissioning protocol Croatia
- Audience: foreign property owners, buyers and investors in Croatia
- Intent: informational

## Page content

Laying expensive parquet or large-format tiles directly over a new heated screed without a proper commissioning protocol (probno grijanje) is a guaranteed way to ruin the floor. New concrete screeds hold massive amounts of trapped moisture and internal tension. The commissioning protocol is a strict, multi-day process of slowly raising and lowering the underfloor heating temperature. It forces the screed to expand, contract, and release moisture before the final floor finishes are glued down.

## The Danger of Trapped Moisture

A standard cement screed takes weeks to dry. If you lay parquet while the screed still contains excess moisture, turning on the underfloor heating will force that moisture up into the wood, causing it to warp, cup, and delaminate from the floor.

## Thermal Expansion and Cracking

Concrete expands when heated. The first time a screed is heated, it undergoes significant thermal stress. If this expansion happens after rigid tiles are installed, the screed will crack underneath, taking the tiles and grout with it.

## The Step-by-Step Protocol

The protocol starts no earlier than 21 days after a standard cement screed is poured (or as specified for rapid screeds). The heating water temperature is initially set low (e.g., 20°C) and increased by a few degrees each day up to the maximum operating temperature, held there, and then slowly cooled down.

## Moisture Measurement (CM Method)

After the protocol is complete, the screed must be tested for residual moisture. In Croatia, professional floor installers use the CM (Calcium Carbide) method. For cement screeds with underfloor heating, the moisture content must typically be below 1.8% before laying wood or tiles.

## Owner Evidence and Handover

Never let a contractor skip this step to save time. The owner or project manager must request a signed commissioning protocol log (zapisnik o probnom grijanju) from the heating engineer. This document is often required by the parquet supplier to maintain the material warranty.

## House Construction in Croatia

Planning, coordination and execution control for new houses and villas

## Contact and verification

- For price, timing, availability or a project-specific commitment, contact BLDR.HR; this page is not a proposal or contract.
- Email: info@bldr.hr
- Telephone: +44 777 68 00005