Villa Kvarner · Opatija / 2026-014

## Site photographs

L01 · 6 Aug 2026 Site record Existing living room Two original olive door units and the stone niche establish the room before strip-out. Existing finishes show age and local damp staining.

T01 · 6 Aug 2026 Site record Terrace before works Existing terracotta and worn plinth recorded in the separate terrace facade bay. Openings and balustrade are retained.

L01 · 18 Sept 2026 Site record Strip-out complete in the living zone Removed finishes and kitchen fittings expose the substrate and selected masonry in the living zone.

L01 · 29 Sept 2026 Site record First-fix services and floor heating Service routes, back boxes and floor heating are visible before covering. Pressure and electrical checks are scheduled separately.

W01 · 5 Oct 2026 Site record Bathroom waterproofing stage Wet-room waterproofing before tiling and sanitary installation, with sealed seams and pipe penetrations.

L01 · 15 Oct 2026 Site record Plaster finish and screed curing Continuous screed and plastered walls await moisture checks and approval for oak flooring.

T01 · 21 Oct 2026 Site record Terrace drainage and membrane The waterproofing stage remains uncovered for review. The optional finish selection has not been ordered or installed.

W01 · 24 Oct 2026 Site record Bathroom tiling in progress Warm porcelain is being fitted; levelling clips and unfinished junctions remain visible. Vanity, WC and shower glass are not yet installed.

L01 · 29 Oct 2026 Site record Kitchen joinery installation Protected flooring and partially fitted cabinetry show the current living-zone state. Worktop, appliances and final furniture follow later.

## Next seven days

- Confirm terrace option D-021 by 3 November before releasing the final stone order.

- Confirm bathroom finish D-022 by 5 November within the existing allowance.

- Continue kitchen fronts and worktop templating; keep floor protection in place.

## Inspection points

- HP-01 · 29 Sept 2026 Completed Services before covering Review pressure-test and electrical inspection records before covering services.

- HP-02 · 5 Oct 2026 Completed Wet-zone membrane before tiles Check corners, penetrations and drainage before tiling.

- HP-03 · 27 Oct 2026 Completed Moisture / finish release Moisture check and flooring approval before oak installation.

- HP-04 · 12 Nov 2026 Scheduled Final electrical and system checks Planned qualified checks and commissioning before handover.

## Contact and verification

- For price, timing, availability or a project-specific commitment, contact BLDR.HR; this page is not a proposal or contract.