Flush Door Subframe Installation: Timing and Precision

Flush doors (filomuro) create a clean, minimalist interior without visible architraves. However, the aluminum subframe must be installed much earlier in the renovation process than standard doors. If the subframe is installed too late, or without proper plasterboard reinforcement, the wall will inevitably crack around the door frame every time the door is slammed.
Timing the Installation
Unlike standard doors which are installed after painting and flooring, flush door subframes must be mounted during the drywall (plasterboard) phase. The aluminum frame is screwed directly to the metal stud profiles before the plasterboard is closed and finished.
Drywall Reinforcement
The metal studs supporting the subframe must be reinforced (usually with UA profiles or timber inserts). Since there is no external architrave to hide movement, any flex in the wall when the door closes will cause the joint compound to crack.
Want flush doors in your interior?
Connect the door detail, wall construction and finished floor levels in one design and execution plan before ordering and installation.
Plan the interior and its execution detailsLeveling and Floor Clearance
The subframe must be perfectly plumb and level. The installer must know the exact finished floor height (including glue and parquet/tiles) to leave the correct clearance under the door panel. A mistake here means the door will drag on the floor or leave a massive gap.
Plastering the Joint
Once the subframe is mounted, the plasterer uses a special fiberglass mesh to bridge the gap between the aluminum edge and the plasterboard. This mesh must be embedded in high-strength joint compound to prevent future hairline cracks.
Final Door Panel
The actual door panel and hinges are installed at the very end of the renovation, after all dusty works, painting, and flooring are completely finished. The panel is then painted with the same wall paint to achieve the invisible effect.