Planning MVHR Ducting Before Pouring Concrete

Aug 2026
BLDR.HR
Mechanical ventilation ducting house construction Croatia — house construction in Croatia with MVHR semi-rigid radial ducts…

Mechanical ventilation with heat recovery (MVHR) is essential for modern, airtight homes. However, the ducting requires significant space and careful planning. Routing these ducts must be finalized before the concrete screed is poured or suspended ceilings are closed.

Confirm floor build-up height early

Semi-rigid radial ducts (typically 75mm or 90mm diameter) are often routed within the floor insulation layer beneath the concrete screed. Ensure the architectural plans specify sufficient floor build-up depth to accommodate the crossing of ventilation ducts, plumbing pipes, and electrical conduits without weakening the screed.

Plan the distribution manifold location

The heart of a radial duct system is the distribution manifold, which connects the main unit to the individual room ducts. Position this manifold centrally to minimize duct lengths, reduce pressure drops, and ensure a quieter system. It is usually placed in a utility room or a dedicated ceiling void.

Coordinate with structural elements

Ducts cannot simply pass through load-bearing concrete beams or steel lintels without prior engineering approval. Plan the vertical risers and horizontal runs to align with structural voids, or specify cast-in penetrations before the concrete is poured to avoid expensive and risky core drilling later.

Protect ducts during construction

Once laid on the concrete slab, exposed plastic ducts are vulnerable to being crushed by workers' boots or equipment before the screed is poured. Mandate clear site rules and temporary protection for the ductwork to prevent hidden damage that will leak air after the house is finished.

Document before covering

Take detailed, high-resolution photographs of the entire duct layout before the insulation and screed are applied. Contact us for comprehensive house construction management that ensures all hidden services are correctly installed and documented before it is too late.