C-008 · Revision B29 October 2026

Cost plan and financial snapshot

Villa Kvarner · Opatija / 2026-014

Approved total
€248,500.00
Available reserve
€12,000.00
Paid
€100,000.00

Financial position

Original agreement
€242,700.00
Approved change CO-001
€5,800.00
Current approved total
€248,500.00
Unallocated owner reserve
€12,000.00
Owner funding envelope
€260,500.00
Pending optional change
€2,400.00
Committed, including certified works
€178,000.00
Certified works
€126,400.00
Invoiced
€119,000.00
Paid
€100,000.00
Certified, not yet invoiced
€7,400.00
Unpaid invoices
€19,000.00
Approved, not yet committed
€70,500.00

Approved options are deducted from the available reserve. Pending options are excluded.

Open detailed cost plan

Invoices and payments

Invoices and payments
DocumentDateAmountPaidOutstanding
INV-001
Design and mobilisation
20 Aug 2026€20,000.00€20,000.00€0.00
INV-002
Strip-out and substrates
18 Sept 2026€25,000.00€25,000.00€0.00
INV-003
Services first-fix
2 Oct 2026€35,000.00€35,000.00€0.00
INV-004
Joinery procurement
16 Oct 2026€20,000.00€20,000.00€0.00
INV-005
Finishes interim valuation
29 Oct 2026€19,000.00€0.00€19,000.00

Procurement and deliveries

Procurement and deliveries
Work packageDateAmountStatus
PO-011 · Kitchen cabinetry29 Oct 2026€13,950.00Part delivered; installation underway
PO-012 · Oak flooring28 Oct 2026€11,281.25Delivered; protected installation
PO-013 · Sanitaryware and tapware5 Nov 2026€10,500.00Awaiting D-022 finish confirmation
PO-014 · Baseline terrace paving3 Nov 2026€2,550.00Awaiting D-021 selection; no order placed
PO-015 · Heat-pump unit12 Nov 2026€8,125.00Delivered; commissioning scheduled