S-003 · Revision B29 October 2026

Programme and hold points

Villa Kvarner · Opatija / 2026-014

Programme
67%
Planned handover
12 Dec 2026
Inspection points
4
Completed
3

Programme

  1. 6 Aug 2026 — 20 Aug 2026Completed

    Survey and scope

    100%

    Concept brief, room schedule and retained fabric recorded.

    100%
  2. 21 Aug 2026 — 12 Sept 2026Completed

    Design and coordination

    100%

    Design proposals and work packages coordinated.

    100%
  3. 14 Sept 2026 — 5 Oct 2026Completed

    Strip-out and first-fix

    100%

    Original structural shell retained; local substrate, services and wet-zone preparation completed.

    100%
  4. 6 Oct 2026 — 27 Nov 2026In progress

    Interiors and fitted joinery

    40%

    Current phase: finishes, kitchen installation and outstanding client selections.

    40%
  5. 30 Nov 2026 — 12 Dec 2026Planned

    Testing, snagging and handover

    0%

    Planned final checks, documentation, cleaning and handover.

    0%

Inspection points

  1. HP-01 · 29 Sept 2026Completed

    Services before covering

    Review pressure-test and electrical inspection records before covering services.

  2. HP-02 · 5 Oct 2026Completed

    Wet-zone membrane before tiles

    Check corners, penetrations and drainage before tiling.

  3. HP-03 · 27 Oct 2026Completed

    Moisture / finish release

    Moisture check and flooring approval before oak installation.

  4. HP-04 · 12 Nov 2026Scheduled

    Final electrical and system checks

    Planned qualified checks and commissioning before handover.

Next seven days

  • Confirm terrace option D-021 by 3 November before releasing the final stone order.
  • Confirm bathroom finish D-022 by 5 November within the existing allowance.
  • Continue kitchen fronts and worktop templating; keep floor protection in place.