Programme and hold points
Villa Kvarner · Opatija / 2026-014
- Programme
- 67%
- Planned handover
- 12 Dec 2026
- Inspection points
- 4
- Completed
- 3
Programme
Survey and scope
100%Concept brief, room schedule and retained fabric recorded.
Design and coordination
100%Design proposals and work packages coordinated.
Strip-out and first-fix
100%Original structural shell retained; local substrate, services and wet-zone preparation completed.
Interiors and fitted joinery
40%Current phase: finishes, kitchen installation and outstanding client selections.
Testing, snagging and handover
0%Planned final checks, documentation, cleaning and handover.
Inspection points
Services before covering
Review pressure-test and electrical inspection records before covering services.
Wet-zone membrane before tiles
Check corners, penetrations and drainage before tiling.
Moisture / finish release
Moisture check and flooring approval before oak installation.
Final electrical and system checks
Planned qualified checks and commissioning before handover.
Next seven days
- Confirm terrace option D-021 by 3 November before releasing the final stone order.
- Confirm bathroom finish D-022 by 5 November within the existing allowance.
- Continue kitchen fronts and worktop templating; keep floor protection in place.