Weekly site report · W44
Villa Kvarner · Opatija / 2026-014
- Project status
- 29 October 2026
- Programme
- 67%
- Planned handover
- 12 Dec 2026
Site photographs

Existing living room
Two original olive door units and the stone niche establish the room before strip-out. Existing finishes show age and local damp staining.

Terrace before works
Existing terracotta and worn plinth recorded in the separate terrace facade bay. Openings and balustrade are retained.

Strip-out complete in the living zone
Removed finishes and kitchen fittings expose the substrate and selected masonry in the living zone.

First-fix services and floor heating
Service routes, back boxes and floor heating are visible before covering. Pressure and electrical checks are scheduled separately.

Bathroom waterproofing stage
Wet-room waterproofing before tiling and sanitary installation, with sealed seams and pipe penetrations.

Plaster finish and screed curing
Continuous screed and plastered walls await moisture checks and approval for oak flooring.

Terrace drainage and membrane
The waterproofing stage remains uncovered for review. The optional finish selection has not been ordered or installed.

Bathroom tiling in progress
Warm porcelain is being fitted; levelling clips and unfinished junctions remain visible. Vanity, WC and shower glass are not yet installed.

Kitchen joinery installation
Protected flooring and partially fitted cabinetry show the current living-zone state. Worktop, appliances and final furniture follow later.
Next seven days
- Confirm terrace option D-021 by 3 November before releasing the final stone order.
- Confirm bathroom finish D-022 by 5 November within the existing allowance.
- Continue kitchen fronts and worktop templating; keep floor protection in place.
Inspection points
Services before covering
Review pressure-test and electrical inspection records before covering services.
Wet-zone membrane before tiles
Check corners, penetrations and drainage before tiling.
Moisture / finish release
Moisture check and flooring approval before oak installation.
Final electrical and system checks
Planned qualified checks and commissioning before handover.