R-014 · Revision A29 October 2026

Weekly site report · W44

Villa Kvarner · Opatija / 2026-014

Project status
29 October 2026
Programme
67%
Planned handover
12 Dec 2026

Site photographs

Existing living room
L01 · 6 Aug 2026Site record

Existing living room

Two original olive door units and the stone niche establish the room before strip-out. Existing finishes show age and local damp staining.

Terrace before works
T01 · 6 Aug 2026Site record

Terrace before works

Existing terracotta and worn plinth recorded in the separate terrace facade bay. Openings and balustrade are retained.

Strip-out complete in the living zone
L01 · 18 Sept 2026Site record

Strip-out complete in the living zone

Removed finishes and kitchen fittings expose the substrate and selected masonry in the living zone.

First-fix services and floor heating
L01 · 29 Sept 2026Site record

First-fix services and floor heating

Service routes, back boxes and floor heating are visible before covering. Pressure and electrical checks are scheduled separately.

Bathroom waterproofing stage
W01 · 5 Oct 2026Site record

Bathroom waterproofing stage

Wet-room waterproofing before tiling and sanitary installation, with sealed seams and pipe penetrations.

Plaster finish and screed curing
L01 · 15 Oct 2026Site record

Plaster finish and screed curing

Continuous screed and plastered walls await moisture checks and approval for oak flooring.

Terrace drainage and membrane
T01 · 21 Oct 2026Site record

Terrace drainage and membrane

The waterproofing stage remains uncovered for review. The optional finish selection has not been ordered or installed.

Bathroom tiling in progress
W01 · 24 Oct 2026Site record

Bathroom tiling in progress

Warm porcelain is being fitted; levelling clips and unfinished junctions remain visible. Vanity, WC and shower glass are not yet installed.

Kitchen joinery installation
L01 · 29 Oct 2026Site record

Kitchen joinery installation

Protected flooring and partially fitted cabinetry show the current living-zone state. Worktop, appliances and final furniture follow later.

Next seven days

  • Confirm terrace option D-021 by 3 November before releasing the final stone order.
  • Confirm bathroom finish D-022 by 5 November within the existing allowance.
  • Continue kitchen fronts and worktop templating; keep floor protection in place.

Inspection points

  1. HP-01 · 29 Sept 2026Completed

    Services before covering

    Review pressure-test and electrical inspection records before covering services.

  2. HP-02 · 5 Oct 2026Completed

    Wet-zone membrane before tiles

    Check corners, penetrations and drainage before tiling.

  3. HP-03 · 27 Oct 2026Completed

    Moisture / finish release

    Moisture check and flooring approval before oak installation.

  4. HP-04 · 12 Nov 2026Scheduled

    Final electrical and system checks

    Planned qualified checks and commissioning before handover.